Name: Contingency Planning & Training Procedures
Effective Date: December 2016
Category: System Management
Version: 1.1
  1. Scope:

    This policy applies to all employees, contractors, temporary personnel, members of boards, commissions and councils, agents, and vendors in the service of L&I.

  2. Procedure:

    This procedure is implemented by various L&I Users from both the Office of Information Technology (OIT), Bureau of Human Resources (BHR) and the business units. This procedure will be initiated by the Chief Information Security Officer (CISO) and Enterprise Security and Compliance Section (ESC) at the direction of the Chief Information Officer (CIO) and Deputy CIO (DCIO). Steps will additionally be completed by the Business Relationship Management (BRM) division, and Enterprise Architecture and Standards section (EAS).

    1. Contingency Planning
      Conducted when required by information system changes and no less than annually.

      Step Responsibility Action
      1. CISO/ ESC / BRM / EAS Update Mission Critical Applications (MCA) list
      2. CISO/ ESC / BRM / EAS Coordinate Business Impact Analysis (BIA) to determine:
      • Maximum Tolerable Downtime (MTD)
      • Return to Operation (RTO) timeline
      • Recovery Point Objective (RPO)
      • Capacity requirements
      3. ESC / BRM/ EAS/ COOP Coordinate review and update of Contingency Plan (CP) with business area
      4. CISO/ ESC / BRM / EAS Coordinate review and update of Disaster Recovery (DR) plan with business area
      5. CISO/ ESC Coordinate review of communications plans for MCA outage and cyberattack with Continuity of Operations Planning (COOP) Coordinator in BHR
      6. CIO/DCIO Coordinate review and update of OIT bureau succession plans
      7. BRM/ COOP Coordinate review and update of business area succession plans

    2. Contingency Training
      Conducted when required by information system changes and no less than annually.

      Step Responsibility Action
      1. CISO/ ESC / BRM Coordinate CP testing
      2. BRM Conduct After Action Review (AAR) following CP testing
      3. BRM Store CP documentation, test results and CP test AAR with CP and share with COOP coordinator
      4. CISO/ ESC / BRM Coordinate DR Plan testing
      5. BRM Conduct After Action Review (AAR) following DR testing
      6. BRM Store DR documentation, test results and DR test AAR with DR plan and share with COOP coordinator
  3. References
    SYM-001 Contingency Planning & Training Policy
    OA ITP-SEC019 - CoPolicy and Procedures for Protecting Commonwealth Electronic Data
    Management Directive 205.41 - Commonwealth of Pennsylvania Continuity of Operations (COOP) Program
    Executive Order 2012-05 - Commonwealth Continuity of Government
    IRS Publication 1075
    SP 800-53 R4 - Security Controls and Assessment Procedures for Federal Information Systems and Organizations
  4. Version Control
    Version Date Purpose
    1.0 06/2016 Base Document
    1.1 12/2016 Content additions and edits